Technical Booklet G Resistance to the Passage of Sound·Page 75·3.61(a)-(e)

Points to watch – Do requirements

Best practice requirements for Floor Type 2 construction including joint filling, workmanship at perimeters, building floor base into walls, mortar filling, and controlling flanking transmission.

(a) Do fill all joints between parts of the floor to avoid air paths. (b) Do give special attention to workmanship and detailing at the perimeter and wherever a pipe or duct penetrates the floor in order to reduce flanking transmission and to avoid air paths. (c) Do build a separating concrete floor base into the walls around its entire perimeter where the walls are masonry. (d) Do fill with mortar any gap that may form between the head of a masonry wall and the underside of the concrete floor. (e) Do control flanking transmission from walls connected to the separating floor as described in the guidance on junctions.